More information about this project:
Integrated Care Centre - Diaries
Posted on 30 May 2008
Monday 12 May to Friday 16 May - A meeting between the Council’s Planning Service, Roads Service and the Integrated Care Centre Design Team took place this week. The purpose of the meeting was to reach agreement on the outstanding planning conditions. The meeting went...
Posted on 16 May 2008
Monday 5 May to Friday 9 May - As work gets into gear on site the final details of the design for the Integrated Care Centre are being formally agreed with the Council’s Planning Service. There are a number of conditions on the planning consent which are to be resolved...
Posted on 9 May 2008
Monday 28 April to Friday 2 May - The official sod-cutting ceremony for the Integrated Care Centre took place on Thursday of this week. This officially marks the beginning of the work. Some preparatory work has already been carried out and the Contractor is now in his...
Posted on 23 Apr 2008
Monday 7 April to Friday 11 April - Site preparation work continues in parallel with discussions on the final proposals for addressing the planning conditions. Updated proposals relating to the car park layout, the landscaping, the design of the wild life corridor and the...
Posted on 4 Apr 2008
Monday 3 March to Friday 28 March - This diary entry covers a 4 week period which for me included a weeks holiday and the Easter weekend. It is amazing how the loss of a few days at work creates an intense catch-up period in which some tasks such as the Director’s Diary...
Posted on 25 Jan 2008
Detailed planning consent for the Integrated Care Centre was granted on 15 January. As usual, there are a number of pre-start conditions on the consent and the Design Team is working with the Council’s Planning Service towards resolving these. We’re aiming to...
Posted on 10 Aug 2007
Detailed discussions regarding the final layout of the Integrated Care Centre are now reaching conclusions which allow a revised planning application to be submitted. We have agreed with the Planning Service the general approach to the planning application and the supporting...
Posted on 9 Feb 2007
The design work for the Integrated Health and Social Care Centre at Woodhead is progressing well. A preferred contractor has been identified for a Design and Build contract. The contractor has been instructed to progress the initial stages of the detailed design, including...
Posted on 5 Jan 2007
• Agreements reached with EDC Social Services and NHS on building specification / requirements
• Design developed to allow planning application and Design and Build tender
• Tender process completed and Preferred Contractor appointed for £7.3M...
Posted on 3 Nov 2006
The preferred contractor for the Integrated Health and Social Care Centre was introduced to the design team this week. This is a significant step towards getting started on site. The tender process is now complete and final negotiations on the details are underway. A number of...