Kirkintilloch Link Road

Posted on 9 Aug 2008

Monday 7 July to Friday 11 July - Now that the main construction contract has been mobilised, the Design and Construction Teams are working hard on all of the arrangements required to get a site start during August. This includes:
• The main site compound being set up by the Contractor at Woodilee Road, close to the Woodilee Industrial Estate.
• The tender programme being updated to take account of lead-in times for sub-contractors and material suppliers.
• Liaison with affected landowners on pre-contract and main contract accommodation works. A key priority is to get the drainage systems in place and working properly between the KLR site and the adjacent fields
• Completing the fencing, removal and treatment of all of the Japanese Knotweed

A Residents Information Pack is being prepared for sending out to those who have responded to our initial letter inviting registration for information updates. I expect this information to be posted out next week.

Link Road Online Survey

Complete our short survey to tell us how you would like to be kept informed about progress on construction of the Link Road

Newsletter

Sign up to our free email update service.

Sign up now

Any Questions

Call us: 0141 578 8272

Email us: info@k-i.org.uk

Partners

East Dunbartonshire Council

NHS Greater Glasgow and Clyde

Kirkintilloch's Initiative
Partnership House
22 Union Street
Kirkintilloch G66 1DH
Tel: 0141 578 8272
Email: info@k-i.org.uk
Kirkintilloch's Initiative